Update on Town-wide Culvert Replacement Projects:

Old Ridge Rd Retaining Wall: Project Completed. 

Ball Rd Culvert: We have experienced some delays at the Ball Road Culvert Replacement project. These delays were caused by three intense rainstorms after work began and underground utilities located closer to the excavation than anticipated. This required a redesign of one wingwall and additional delays from Orange & Rockland to move utilities before work could continue. I’m pleased to report that these issues have been resolved. The culvert, wingwalls, and retaining wall with drainage pipe are now installed. Final grading, subbase, and binder paving will be completed this week. Guiderail installation is scheduled for August 13–14, followed by the top course of pavement, topsoil, and seeding. If the weather cooperates, Ball Road will reopen by the end of next week. 

Hoyt Road Culvert: Backfilling is complete, and the sub-base and binder have been installed. Guiderail installation, handled by a subcontractor, is scheduled for Monday and Tuesday, August 11–12. Following this work, the contractor will complete the top course of pavement, topsoil, seeding, and any remaining punch list items. If the subcontractor remains on schedule and weather cooperates, Hoyt Road is expected to reopen by the end of next week.

Pumpkin Hill Road Culvert: Footings are being installed today and tomorrow, with culvert and wingwall deliveries and installations planned for later this week. The contractor is coordinating the remaining work items, and the road is expected to reopen in approximately three to four weeks.

Cascade Road Culvert: Construction is scheduled to begin Wednesday, August 6th. Installation of the precast concrete components using a crane is set for August 12–14. During this period (12- 14), the “triangle” (intersection of Brady and Cascade) will be closed, and Cascade Road will be accessible only from the Route 17A end. Cascade Road will remain OPEN for the three-to-four-week duration of the project excluding the 12th through the 14th. There is no safe way to operate the crane with the triangle open during that time. 

Warwick Area Farmworker Organization will host Dulce Esperanza, a Kermes fundraiser for the summer school program.  This event will be held on Sunday, August 10th from 12:00 to 4 p.m. at Pine Island Park, Pine Island.  Delicious, authentic food available for purchase. If you need additional information, please call (845) 258-1560.    

Fuller Moon Arts Festival at Mountain Lake Park, 46 Bowen Road, Warwick on Saturday, August 16th from 1-9 pm (rain date: Sun. Aug. 17).  This family friendly event is sponsored by Wickham Works and Warwick Center for the Performing Arts and will feature art, performances, and entertainment along with food trucks and a bar truck. Single entrance fee is $20 for adults, $15 for children, senior adults and a family discount pass for the day. 

Stop by Town Hall and pick up your Senior Barbeque tickets in the Supervisor’s Office, Monday through Friday, 8:30 a.m. to 4 p.m. This year the barbeque will take place on Tuesday, August 19th (rain date: Aug. 20th) starting at 11 a.m. at Warwick Town Park on Union Corners Road.  This event is co-sponsored by the Warwick Valley Rotary Club and our Town of Warwick DPW. The event is made possible and supported by many local organizations that serve our town’s senior population. 

The next regular meeting of the Town Board will be held on Thursday, August 14th, 2025 at 7:00 p.m. at Warwick Town Hall, 132 Kings Highway. A public workshop of the Town Board may take place up to 90 minutes prior to the regular scheduled meeting. The meeting will be streamed live on the Town of Warwick’s Facebook page and YouTube channel as well as Channel 21 of your cable box.